Tottingworth Park · East Sussex · Case study

Moving treatment away from the propertyfor a landscaping project

A BIOROCK Monoblock 3-1000 was installed around 30 metres from the old septic tank, with a gravity outfall running approximately 70 metres.

Discuss a similar project
Rural sewage treatment plant project at Tottingworth Park
LocationTottingworth Park

Rural East Sussex property

SystemBIOROCK Monoblock 3-1000

A non-electric treatment arrangement

PositionAround 30 metres from the old tank

Moved away from the property for planned landscaping

OutfallAround 70 metres

Gravity outfall to the watercourse below

01 · The situation

A septic tank discharging to a pond

The original case study records a non-compliant septic tank discharge to a pond that overflowed to a watercourse. A landscaping project was also planned for the property.

02 · The recorded installation

A non-powered system in a new position

A BIOROCK Monoblock 3-1000 was installed around 30 metres from the old septic tank. The published case study records that the system required no power and produced no noise.

Project details

01

The starting point

The old septic tank discharged to a pond that overflowed to a watercourse, and a landscaping project was planned for the property.

02

The solution

A BIOROCK Monoblock 3-1000 was installed approximately 30 metres from the old tank position.

03

The work

A gravity outfall was run approximately 70 metres to the watercourse below.

04

The result

The completed installation used a gravity-discharge system rated for six to eight people and required no power.

Planning a replacement or new installation?

Tell us about the property, the current system and what you need to achieve. We can discuss the practical next step.