The original case study records a non-compliant septic tank discharge to a pond that overflowed to a watercourse. A landscaping project was also planned for the property.
A non-powered system in a new position
A BIOROCK Monoblock 3-1000 was installed around 30 metres from the old septic tank. The published case study records that the system required no power and produced no noise.
Project details
The starting point
The old septic tank discharged to a pond that overflowed to a watercourse, and a landscaping project was planned for the property.
The solution
A BIOROCK Monoblock 3-1000 was installed approximately 30 metres from the old tank position.
The work
A gravity outfall was run approximately 70 metres to the watercourse below.
The result
The completed installation used a gravity-discharge system rated for six to eight people and required no power.
Project photographs
The rural site, excavation, treatment unit and the longer drainage route across the property.





Planning a replacement or new installation?
Tell us about the property, the current system and what you need to achieve. We can discuss the practical next step.